Build Blog, p 3

All the groundwork now completed, we got down to 1 meter and hit chalk which is just great, all the ground drainage is done and the sewers are installed. I got out my old tool chest and replumbed the kitchen equipment so we can operate the dishwasher, washing machine etcetera, it really is so easy nowadays with all the plastic mouldings, in my day it was pipe benders and soldering but this stuff is just fantastic.
The bricks arrive tomorrow but I have a snag, the carpenter I was going to use has now taken on a bigger job so I have a panic in about two weeks, hopefully I'll get a replacement by then.
The plan was to get the roof on by xmas but if that falls through I must pray for no rain.
Paid the first bill, 7200 for all the groundworks.
Braddock, VC is online now Find More Posts by Braddock, VC
RCG Plus Member
Latest blog entry: Reverse Takeover
Reply With Quote
Sign up now
to remove ads between posts
Reply

Thread Tools

Similar Threads
Category Thread Thread Starter Forum Replies Last Post
Build Log P-3 Orion 1/19.3 scale build air tanker Midnight Express Scale Kit/Scratch Built 28 Jun 04, 2013 05:22 PM
Discussion Build Video or Blog?? crash74 Electric Plane Talk 0 Aug 26, 2012 09:06 PM
Discussion Autonomous hexacopter / rover build and testing blog batfire Multirotor Talk 0 Aug 21, 2012 02:38 PM