Last week was a very slow week. Work had me slammed. I had to clean up the fuse as once I started getting it ready to import into 3D I saw many many problems. So if I had to guess I would say I redesigned 50% of the fuse work I had done. To date I have about 170 hours in this design. This project as far as design and getting it into CAD started June of last year. I am very happy with the nacelles also.

I still have about 10 hours of cleaning up to do, but that will take a few weeks as the 36 is getting all my time when I can make noise.